October 29, 2019

The contractor spent most of last week prepping and installing several catch basins at the site. Also impact panels were poured at the bridge approaches and are now curing. At the same time, guard rails were formed along each side of the bridge and will hopefully be poured later this week. Sub grade prepping for the road base will continue.

The forms for the bridge guard rails.Recently Completed Work

  • Set catch basin and running pipe.
  • Formed and poured impact panels.
  • Formed guard rails.
  • Began grading road.
catch basin installationsThis Week's Work
  • Pour and cure guard rails.
  • Continue grading road.