September 1, 2017
Installing first section of Beaver Creek steel culvert under Stark St.

Construction:  

All concrete footings have been poured for the culvert and walls. The contractor has started to install sections of the steel arch culvert, which are bolted together.  Assembly of the steel culvert continues next week, in addition to building forms for the concrete walls.  The head walls on the downstream side of the culvert will be poured the week of September 5.

Next week work will begin on the streambed inside the culvert, where boulders will be placed to create resting pools for migrating fish.

The current schedule shows Stark Street reopening to traffic in early October.

Website:  https://multco.us/roads/webform/stark-street-culvert-replacement

Crane lifting form for Beaver Creek culvert headwall, August 2017