Removal of old Sellwood Bridge marks end of an era

July 13, 2016

Sections of the old Sellwood Bridge have been removed, with short segments coming down next.

After 90 years of serving the public, the original Sellwood Bridge will be only a memory by the end of this summer. The last steel span of the original bridge was lowered to a barge on July 12.  Removing the old bridge has been one of the most visually interesting parts of the Sellwood project, with many people watching as a familiar landmark slowly disappears.

To understand how the bridge is being deconstructed, it helps to remember its history.

  • The Sellwood Bridge was built in 1925. To save money, the bridge was built as one continuous 1100-foot long four-span truss perched on concrete piers.
  • In January 2013, the steel truss was slid north and attached to temporary steel piers, which allowed the bridge to be open to traffic while the contractor built the new Sellwood Bridge on the same alignment as the original bridge. Traffic continued to use the old bridge in its new location for three years while the new bridge was built.
  • When the new bridge opened on February 29, 2016, the original bridge closed and the contractor began the complicated task of removing the old bridge and its temporary supports.

About the demolition team

Since the old bridge was built as one continuous 1100-foot long span, it could not easily be dismantled and removed in sections. It was also coated in lead-based paint, a known health hazard. A specialized team was assembled to deal with these challenges and get the old bridge safely down.

General contractor Slayden-Sundt and McGee Engineering teamed with Emmert International of Clackamas. Emmert International has moved complicated structures ranging from the Spruce Goose (the gigantic wood airplane built by Howard Hughes, which was delivered to the Evergreen Aviation and Space Museum in McMinnville) to the Hotel Fairmount in San Antonio (the largest building ever moved on wheels).

A complicated project

In the past (and still in some parts of the world today) old bridges are taken down with explosives. This has not been done in Oregon for decades, for obvious environmental and safety reasons. Instead, the old Sellwood Bridge is being cut into sections and carefully lowered by hydraulic jacks onto a barge, which will minimize impacts to neighbors, nearby structures, fish species and water quality. 

Removing concrete railing from old Sellwood Bridge.
Removing concrete railing from old Sellwood Bridge.

Lowering truss span to a barge.
Lowering truss span to a barge.
Cutting a thousand-foot-long bridge into sections is not straightforward. Subcontractor Staton Companies began the demolition process by cutting and removing the concrete deck, railings and sidewalk from the old bridge, leaving the green steel skeleton of the truss spans sitting on steel supports. About 2,300 tons (4.6 million pounds) of concrete was removed and recycled as fill material for construction projects.

Strengthening steel was then added to the temporary piers and truss section to counter the forces applied during lowering. Long steel tie-downs were attached to the stub ends of the truss spans to hold the sections in place after the center sections were cut and lowered.

Finally, the cutting began. Workers used oxy-acetylene torches to cut the steel truss span free at each end. The truss span is 28 feet high, so cutting each span section free took at least one day.

The spans were then lowered 50 or 60 feet onto the decks of the barges. The team started lowering each span around dawn and completed the process by evening. Each section weighed between 400,000 and 500,000 pounds and had to be lowered perfectly in unison onto the barge.

Each span was then cut into two or three sections to fit on separate barges and taken ten miles north to the Schnitzer Steel facility, where they were processed for recycling.

Next steps

The in-water work period began in July. After the truss spans and steel supports are removed, a marine subcontractor will begin removing the 80 steel piles that supported the temporary bridge. By this fall, there will be no remaining sign of the old bridge. The new Sellwood Bridge will have the view all to itself.

For more information, visit sellwoodbridge.org.

Spans from the old Sellwood Bridge sit on barges before delivery to a recycler.