Several County roads to close for Portland Water Bureau’s “Fix-It First” improvement work

August 23, 2024

Starting next week, several roads maintained by Multnomah County Transportation will close for work related to the Portland Water Bureau’s “Fix-It First” road improvement work. During these closures local and emergency access will be maintained.

S.E. Lusted Road 

Aug. 26-27 - On Monday, Aug. 26 and Tuesday, Aug. 27 S.E. Lusted Road between S.E. Cottrell Road and just east of S.E. Altman Road will be closed from 7:00 a.m. to 7:00 p.m. 

S.E. Altman Road (south of S.E. Dodge Park Boulevard)

Aug. 26 – On Monday, Aug. 26, S.E. Altman Road between S.E. Dodge Park Boulevard and the County line will be closed from 7:00 a.m to 7:00 p.m. 

Aug. 27-29 – On Tuesday, Aug 27 through Thursday, Aug. 29 S.E. Altman Road between S.E. Dodge Park Boulevard and the County line will be closed all day and night. 

Aug. 30 – On Friday, Aug. 30, S.E. Altman Road between S.E. Dodge Park Boulevard and the County line will be closed from 7:00 a.m to 7:00 p.m. 

S.E. Hosner Road

Aug. 28-29 - On Wednesday, Aug. 28 and Thursday, Aug. 29 S.E. Hosner Road between N.W. Oxbow Drive and S.E. Lusted Road will be closed from 7:00 a.m. to 7:00 p.m. 

S.E. Altman Road (north of S.E. Dodge Park Boulevard)

Aug. 28 – On Wednesday, Aug. 28 S.E. Altman Road between S.E. Lusted Road and S.E. Dodge Park Boulevard will be closed from 7:00 a.m. to 7:00 p.m.

Aug. 29-31 – On Thursday, Aug. 29 through Saturday, Aug. 31 S.E. Altman Road between S.E. Lusted Road and S.E. Dodge Park Boulevard will be closed continuously. The road will reopen with an unpaved surface at 5:00 p.m. Saturday. Aug. 31. 

Aug. 31-Sept. 4 – On Saturday Aug. 31 S.E. Altman Road between S.E. Lusted Road and S.E. Dodge Park Boulevard will reopen at 5:00 p.m. and will remain unpaved through Wednesday, Sept. 4 at 7:00 a.m.

Sept. 4 - On Wednesday, Sept. 4 S.E. Altman Road between S.E. Lusted Road and S.E. Dodge Park Boulevard will be closed from 7:00 a.m. to 7:00 p.m.

Multnomah County maintains 269 miles of roads. For information, visit: https://www.multco.us/roads

For information and questions related to the Portland Water Bureau’s work, contact:

Project Communications Coordinator, Bonita Oswald: bullrunprojects@portlandoregon.gov.     

Individuals seeking future project updates should visit the City’s project web page at: https://www.portland.gov/water/bullruntreatment/filtration