Hawthorne Bridge Control System Upgrade

We are replacing the control system that opens and closes the Hawthorne Bridge, and upgrading its electrical system.

Project Information

  • Location: Hawthorne Bridge
  • Schedule: Spring 2025
  • Estimated Cost: $750,000
  • Funding Source: 100% county-funded

Project Description

We are replacing the control system that helps operate the Hawthorne Bridge. This includes the computer that allows us to send instructions, the drives that use those instructions to move the drawbridge, and other controls.

We are also upgrading the electrical system before upgrading the control system.

The new system will be more reliable. It will be easier to use and maintain. It will also provide more data to monitor the health of the bridge and give feedback to bridge operators.

Traffic Impacts

There will be daytime lane closures from Monday, March 31 through Wednesday, April 2.

The bridge will be closed to all traffic from Thursday, April 3 through Sunday, April 6.


We are interested in your feedback on this project. Please fill in the form below if you have comments, questions or suggestions.
 