This project replaced the control system that helps operate the Broadway Bridge drawbridge. Two weekend bridge closures were required in August and September 2021.

Project Information

The computer operating system that opens the Broadway Bridge drawbridge is being replaced in 2021.
The computerized system that opens the Broadway Bridge drawbridge is being replaced in 2021.
  • Location: Broadway Bridge
  • Schedule: August to September 2021
  • Funding Source: 100% county-funded

Project Description

This project replaced the control system that helps operate the Broadway Bridge drawbridge. This includes the computer that allows us to send instructions, the drives that use those instructions to move the drawbridge, and touch screens and other controls.

This also includes the computer that controls some overhead equipment for the Portland Streetcar.

The new system will be more reliable. It will be easier to use and maintain. It will also provide more data to monitor the health of the bridge and give feedback to bridge operators.

Schedule

There were two full bridge closures:

  • Saturday-Monday, August 21-23
  • Saturday-Monday, September 18-20

Additional work in August and September had minimal effects on bridge users.

Traffic Impacts

During the closures, the bridge was fully closed to all road, pedestrian and bicycle traffic, and the streetcar did not cross the bridge. These closures were from 6am to 6pm each day.

There were additional minor delays at other times during the project, similar to a normal bridge lift lasting about 20 minutes. The work required outside lanes to be closed some weekdays between 8 am and 3:30 pm. The center lanes were always open, except during the full bridge closures on weekends.

At least one leaf of the drawbridge was able to open at any time to allow vessels to pass. Single leaf openings of the drawbridge happened from August 2 through September 26, 2021. River traffic could request a tugboat assist if needed by contacting the Hawthorne Bridge operator.

The Portland Streetcar announced service changes during the closure.