Portland Water Bureau applied for and was approved to build a drinking water filtration facility and communications tower located at the eastern end of SE Carpenter Road, with raw and finished water pipelines connecting to the existing Bull Run conduit system.
Current Status
On January 22, 2025 the Land Use Board of Appeals (LUBA) remanded the County Hearings Officer’s decision back to the county for review.
No party asked the Oregon Court of Appeals to review the LUBA decision by the February 12, 2025 deadline. As of February 14, 2025, the Portland Water Bureau has begun to wind down the active construction of the Bull Run Filtration project.
Additional information may be available at the Portland Water Bureau’s website.
The county is reviewing the remand and considering options for the remand hearing. The exact time, date and location has not yet been determined.
Documents
- Document
All exhibits in the record, including current permits, can be found in the Document Library
Contact Information
- For information on the LUBA appeal, visit the website for the Land Use Board of Appeals.
- For information on Transportation Planning or Land Use Planning requirements outlined in the Hearings Officer Decision, check this website for updates.
For all other inquiries related to requirements outlined in the Hearings Officer Decision or subsequent permits issued by Multnomah County, please contact landuse-transport-inquiries@multco.us.