The Willamette River Bridges Capital Improvement Plan identifies 56 projects to improve and maintain our bridges. Each project is ranked based on the county's criteria.
Projects are grouped by their target construction time as of 2015. They are then ranked by priority within these time frames. The construction costs are based on estimates of inflation for the target time.
Project Rank | Bridge Name(s) | Project Name | Primary Work Category | Project ID # | Importance Score | Target Construction Time | Total Cost at Target Construction Time |
---|---|---|---|---|---|---|---|
1 | Burnside | Seismic Resiliency (Major Bridge Rehabilitation / Bridge Replacement) - Feasibility Study | Seismic | BUN-BU-12 | TI-1 64.27 | 2015-2019 | $3,000,000 |
2 | Burnside | Seismic Resiliency (Major Bridge Rehabilitation / Bridge Replacement) - Environmental Impact Study | Seismic | BUN-BU-13 | TI-1 64.27 | 2015-2019 | $17,000,000 |
3 | Broadway | Rall Wheel Rehabilitation | Mechanical | BUN-BR-02 | TI-1 48.03 | 2015-2019 | $15,423,401 |
4 | Burnside | 2016 Burnside Rehabilitation Project | Structural | BUN-BU-06 | TI-1 41.73 | 2015-2019 | $30,846,519 |
5 | Morrison | Bridge Painting & Structural Rehabilitation - West Approach | Paint | BUN-MO-09 | TI-1 25.63 | 2015-2019 | $17,159,972 |
6 | Broadway, Burnside, Hawthorne and Morrison | Bicycle and Pedestrian Improvement Project - Feasibility Study Phase | Accessibility | BUN-MU-04 | TI-1 21.96 | 2015-2019 | $1,442,557 |
7 | Broadway | Bridge Painting - 2015 Paint Project | Paint | BUN-BR-13 | TI-1 17.14 | 2015-2019 | $12,658,907 |
8 | Morrison | Bent Cap Rehabilitation - Approach Spans | Structural | BUN-MO-10 | TI-1 9.66 | 2015-2019 | $3,479,386 |
9 | Morrison | Motor, Brake, and Electrical Power Rehabilitation; Operator House Improvements | Mechanical | BUN-MO-01 | TI-1 7.99 | 2015-2019 | $1,649,105 |
10 | Morrison | Painting and Structural Improvements - River Spans | Paint | BUN-MO-14 | TI-1 7.73 | 2015-2019 | $22,773,510 |
11 | Morrison | Roadway Approaches, Bridge Deck Overlay, and Illumination Improvements | Driving Surface | BUN-MO-07 | TI-2 33.33 | 2020-2024 | $13,014,918 |
12 | Broadway | Gate, Span Lock and Structural Rehabilitation - River Spans | Electrical and Lighting | BUN-BR-10 | TI-2 31.07 | 2020-2024 | $4,579,643 |
13 | Broadway | Roadway and Structural Rehabilitation | Driving Surface | BUN-BR-11 | TI-2 30.16 | 2020-2024 | $2,209,311 |
14 | Hawthorne | Bent Cap Rehabilitation - Approach Spans | Structural | BUN-HA-08 | TI-2 25.94 | 2020-2024 | $3,814,227 |
15 | Morrison | Span Lock and Support Rehabilitation | Mechanical | BUN-MO-02 | TI-2 24.45 | 2020-2024 | $1,328,430 |
16 | Broadway | Bridge Deck / Rail / Illumination Improvements | Driving Surface | BUN-BR-07 | TI-2 23.18 | 2020-2024 | $6,130,398 |
17 | Hawthorne | Span Lock and Live Load Shoe Rehabilitation | Mechanical | BUN-HA-02 | TI-2 22.93 | 2020-2024 | $1,001,567 |
18 | Broadway | Broadway Bridge West Approach Structural Rehabilitation and Paint | Paint | BUN-BR-09 | TI-2 21.49 | 2020-2024 | $20,311,661 |
19 | Hawthorne | Operating Machinery, Trunnion, and Trunnion Tower Structural Rehabilitation | Mechanical | BUN-HA-01 | TI-2 21.23 | 2020-2024 | $17,914,399 |
20 | Sauvie Island | Roadway Improvements - East Approach | Driving Surface | BUN-SI-02 | TI-2 17.28 | 2020-2024 | $1,488,668 |
21 | Hawthorne | Joint Rehabilitation and Replacement - West and East Approaches | Structural | BUN-HA-12 | TI-2 17.23 | 2020-2024 | $1,928,296 |
22 | Hawthorne | Structural Rehabilitation of Steel and Concrete Members - River Spans | Structural | BUN-HA-10 | TI-2 16.03 | 2020-2024 | $11,961,361 |
23 | Sauvie Island | Roadway and Structural Rehabilitation | Structural | BUN-SI-03 | TI-2 15.98 | 2020-2024 | $1,371,606 |
24 | Burnside, Broadway, Morrison | Submarine Cable Removal | Electrical and Lighting | BUN-MU-01 | TI-2 15.60 | 2020-2024 | $4,552,476 |
25 | Broadway, Burnside, Hawthorne and Morrison | Bicycle and Pedestrian Improvement Project - Design and Construction Phase 1 | Accessibility | BUN-MU-05 | TI-2 15.14 | 2020-2024 | $16,319,707 |
26 | Broadway, Burnside, Hawthorne and Morrison | Scour Remediation | Structural | BUN-MU-02 | TI-2 14.68 | 2020-2024 | $22,302,695 |
27 | Hawthorne | Hawthorne Bridge Limited Seismic Retrofit | Seismic | BUN-HA-06 | TI-3 170.72 | 2025-2029 | $44,886,391 |
28 | Broadway | Broadway Bridge Limited Seismic Retrofit | Seismic | BUN-BR-06 | TI-3 92.66 | 2025-2029 | $52,628,358 |
29 | Burnside | Seismic Resiliency (Major Bridge Rehabilitation / Bridge Replacement) - Final Design and Construction | Seismic | BUN-BU-07 | TI-3 89.15 | 2025-2029 | $496,070,564 |
30 | Morrison | Morrison Bridge Limited Seismic Retrofit | Seismic | BUN-MO-05 | TI-3 73.37 | 2025-2029 | $91,883,919 |
31 | Morrison | Structural Rehabilitation of Steel and Concrete Pier Members - River Spans | Structural | BUN-MO-11 | TI-3 51.62 | 2025-2029 | $14,103,949 |
32 | Hawthorne | Roadway, Sign Bridge, Bridge Deck and Illumination Improvements - Approaches | Structural | BUN-HA-07 | TI-3 38.96 | 2025-2029 | $25,679,708 |
33 | Hawthorne | Paint and Structural Rehabilitation of Steel and Concrete Members - East Approach | Paint | BUN-HA-11 | TI-3 31.49 | 2025-2029 | $35,447,056 |
34 | Morrison | Joint Rehabilitation - West Approach, River Spans and East Approach | Structural | BUN-MO-13 | TI-3 24.77 | 2025-2029 | $3,837,233 |
35 | Broadway | Movable Span Deck Replacement | Driving Surface | BUN-BR-16 | TI-3 22.73 | 2025-2029 | $10,148,330 |
36 | Hawthorne | Bridge Painting and Upgraded Lighting | Paint | BUN-HA-13 | TI-3 21.59 | 2025-2029 | $43,328,584 |
37 | Broadway, Burnside, Hawthorne and Morrison | Bicycle and Pedestrian Improvement Project - Design and Construction Phase 2 | Accessibility | BUN-MU-06 | TI-3 20.31 | 2025-2029 | $16,323,533 |
38 | Broadway, Burnside, Hawthorne and Morrison | Fender Repair and Installation | Structural | BUN-MU-03 | TI-3 14.04 | 2025-2029 | $43,142,056 |
39 | Broadway | Bridge Painting - Maintenance of 2002 Paint Project | Paint | BUN-BR-12 | TI-4 45.06 | 2030-2034 | $66,631,927 |
40 | Morrison | Paint, Structural Rehabilitation and Access Improvements - East Approach | Paint | BUN-MO-12 | TI-4 42.79 | 2030-2034 | $54,416,301 |
41 | Broadway | Operating Machinery Rehabilitation and Brake Replacement | Mechanical | BUN-BR-01 | TI-4 31.52 | 2030-2034 | $2,300,579 |
42 | Morrison | Warning Gate and Sign Bridge Replacement | Electrical and Lighting | BUN-MO-06 | TI-4 23.01 | 2030-2034 | $6,631,895 |
43 | Broadway | Electrical System Master Control Switch Installation and Miscellaneous Operator House Improvements | Electrical and Lighting | BUN-BR-03 | TI-4 18.66 | 2030-2034 | $307,377 |
44 | Broadway | Bridge Painting - Maintenance of 2015 Paint Project | Paint | BUN-BR-14 | TI-4 16.65 | 2030-2034 | $14,891,720 |
45 | Sellwood | Lighting Maintenance | Electrical and Lighting | BUN-SE-01 | TI-4 14.26 | 2030-2034 | $326,903 |
46 | Sellwood | Joint Rehabilitation and Replacement | Structural | BUN-SE-02 | TI-4 14.16 | 2030-2034 | $353,055 |
47 | Hawthorne | Installation of Remote Operation and Monitoring Equipment | Electrical and Lighting | BUN-HA-04 | TI-4 13.58 | 2030-2034 | $2,063,574 |
48 | Hawthorne | ADA Improvements | Accessibility | BUN-HA-14 | TI-4 12.02 | 2030-2034 | $3,703,257 |
49 | Morrison | ADA Improvements | Accessibility | BUN-MO-15 | TI-4 9.57 | 2030-2034 | $3,703,257 |
50 | Broadway | ADA Improvements | Accessibility | BUN-BR-15 | TI-4 9.57 | 2030-2034 | $1,875,456 |
51 | Sauvie Island | Under-bridge Maintenance Traveler System | Structural | BUN-SI-04 | TI-4 8.19 | 2030-2034 | $510,786 |
52 | Morrison | Installation of Remote Operation and Monitoring Equipment | Electrical and Lighting | BUN-MO-03 | TI-4 8.15 | 2030-2034 | $2,063,574 |
53 | Broadway | Installation of Remote Operation and Monitoring Equipment | Electrical and Lighting | BUN-BR-04 | TI-4 8.15 | 2030-2034 | $2,063,574 |
54 | Sauvie Island | Routine Maintenance and Bridge Painting | Paint | BUN-SI-01 | TI-4 5.87 | 2030-2034 | $560,741 |
55 | Hawthorne | Warning and Barrier Gate Rehabilitation | Electrical and Lighting | BUN-HA-03 | TI-4 3.86 | 2030-2034 | $3,674,718 |
56 | Sellwood | Bridge Maintenance Painting | Paint | BUN-SE-03 | TI-4 2.93 | 2030-2034 | $774,760 |