Our permit process moved online as of Monday, October 30, 2023.
Before You Submit
If your project requires a land use permit(s), you must obtain approval of the permit(s) prior to submitting your building plans for zoning review.
Submitting Your Plan
You are ready to submit your building plans if:
- our Planner on Duty has given you a zoning checklist
- you have obtained all applicable land use permits for the property
Required documents:
- DocumentApplication Form (Type I - IV) (234.48 KB)
- Site Plan
- Floor Plan
- Building Elevations
- Service Provider Review Forms
- Other information identified in your zoning checklist or land use permit
All documents must be submitted in digital form. Plans must be drawn to scale, either engineering or architect.
If you have followed your checklist and have all your required documents, you may submit your plan through the customer portal. In the portal, select the Zoning Plan Review application option.
After You Submit
We will respond in the order requests were received. If your request meets the basic requirements, you will receive an invoice with your application fees in the customer portal. The fees must be paid for the application to be considered ‘received’. See our fee schedule.
After your application is received, the assigned planner will send you a status update in 30 days.