Project Information
- Location: NW Rocky Point Road, 1500’ south of Hwy 30 (map)
- Schedule: Summer 2025
- Estimated Cost: $450,000
- Funding Source: Local Funds
Project Description
We will remove and replace a failed culvert that is causing a sinkhole next to NW Rocky Point Road. The current 18” culvert will be replaced with a 24” culvert to reduce the chance of future road failure.
Traffic Impacts
Rocky Point will be fully closed to all traffic at the culvert location for up to 30 days.
Traffic will be detoured to NW Logie Trail and NW Skyline Blvd to reach Rocky Point south of the closure.
We are interested in your feedback on this project. Please fill in the form below if you have comments, questions or suggestions.