Additional safety improvements are coming to Multnomah County’s section of NW Cornelius Pass Road in 2019.  The Oregon Legislature allocated funding to Multnomah County for the improvements.  

Public Meeting

A public meeting on the improvements was held on January 5, 2017 at Skyline Elementary School. The project team provided an update on the project's design, which has reached the 30% level and a preview of construction, which is planned for 2019, when NW Newberry Road will be open and available as a detour for cars and small trucks.

The meeting presentation is below.

Project Elements

Safety improvements that are currently proposed include:

  • 8th Avenue Intersection:
    • Signage (to be included with corridor wide signing upgrades)
    • Vegetation and obstructions removal to improve the horizontal sight line
    • Shoulder widening to six-foot width on both sides of the road
    • Minor curve realignment to replace the existing compound curve with a single curve
  • Boyd’s Lower Driveway (Milepost 2.8):
    • Signage (to be included with corridor wide signing upgrades)
  • Curves 6 & 7 (Milepost 2.8 - 3):
    • Signage (to be included with corridor wide signing upgrades)
    • Provide flashing warning beacons ahead of curves 6 and 7
    • Reconstruction and realignment of the tangent between curves 6 and 7 to eliminate
    • the large radius curve currently connecting them
    • Re-striping lane lines through curves 6 and 7 to accommodate truck-off-tracking
    • Shoulder widening at the apex of curve 7
    • Drainage facilities along the concrete barrier
    • New concrete barrier
  • Curve 3 & 4 (Milepost 3.8/South of Plainview Road):
    • Signage (to be included with corridor wide signing upgrades)
    • Vegetation removal for sight distance improvements
    • Shoulder widening to increase the paved shoulder width to six feet
    • Guardrail upgrades at 3/“S” Curves
  • Kaiser Road Intersection:
    • Signage (to be included with corridor wide signing upgrades)
    • Vegetation removal for sight distance improvements
    • Vehicle activated signs (i.e. "Stopped Vehicle Ahead")
  • Corridor-wide:
    • Comprehensive signing upgrades
    • Vehicle pullouts (police, refuge, mailbox, school bus) at multiple  locations
    • Existing roadside barrier/guardrail analysis and upgrades for existing deficiencies
    • Reduce pavement drop-offs with gravel shoulder wedge where needed
    • Consideration of two variable message signs

The designs prepared by a consultant will be reviewed with staff at Multnomah County and ODOT as well as the general public. The goal is to confirm the designs at the 30% level so the consultant can move forward with final design in 2017.

Schedule

The project is in final design, expected to go to bid in 2018. Construction is expected in 2019, after NW Newberry Road (currently closed due to a landslide) has been repaired and reopened to serve as a detour for cars and small trucks during the work on Cornelius Pass Road. 

Project Background

The Cornelius Pass Road Safety Evaluation JTA Final Report was provided by the Oregon Department of Transportation (ODOT) to the Oregon Legislature early in 2011. The final report with appendices is available through the ODOT Region 1 website.   

The 2013 Oregon Legislature reallocated $8.5 million of the project's funding to other Oregon projects that were in need of immediate funding and ready to construct. In 2014 the project experienced a funding shortfall that required a temporary halt to design work. In 2015 Multnomah County was able to secure additional funds from ODOT so that design work could resume. Due to the funding challenges improvements at NW Skyline Blvd. have been dropped from the project. 

In 2013-14 a project team analyzed the most recent data for crashes on the county’s section of Cornelius Pass Road and developed a list of possible safety improvements.  A 15-member Community Advisory Committee (CAC) was recruited to review and provide input on safety improvements for this section of road.  The committee includes representatives from local neighborhoods, a local business, commuters, the trucking industry, and the Oregon Legislature. 

Committee meetings are open to the public.  Meeting materials are posted below as they become available.  To receive notification of meetings, or communicate with the project team or the committee, contact us by e-mail at corneliuspass@multco.us.  

View Map


We are interested in your feedback on this project. Please fill in the form below if you have comments, questions or suggestions.

You must have Javascript enabled to use this form.