Project Information
- Location: SW 257th Avenue, between Historic Columbia River Highway and SE Stark Street
- Schedule: Planned start February 2025
- Estimated Cost: $8 million
- Funding Sources: County Roadway Funds, with $600k from the Mid-County Lighting District and $45k in state funds
Project Description
- Document
- Document
We are making safety improvements to SW 257th Avenue to make it easier and safer for all users to get around the corridor. SW 257th is one of the most heavily traveled roads in Troutdale and provides an important connection to I-84 and US 26.
We will repave the road, install new lighting, and build new curb ramps throughout the corridor. Other options have been designed based on the community's input. These include pedestrian crossings, better bike lanes, improved bus stops and more. Learn more about the project features.
Currently, SW 257th is not a comfortable street for people to walk, ride a bike, or use transit. Heavy traffic from vehicles and large trucks and a high posted speed contribute to safety issues in this corridor. The corridor has sidewalks and bike lanes throughout, but the conditions are not welcoming. The bike lanes and sidewalks are narrow and have no buffer from high-speed traffic. The sidewalks are obstructed by utility poles and vegetation.
The project is mostly funded by the Multnomah County Road Fund. $600,000 will be provided for lighting improvements by the Mid-County Lighting District. $45,000 will be provided from State Funded Local Projects (SFLP) funds managed by ODOT to construct green bike boxes on SW 257th and SW Sturges Drive.
Timeline
Construction is planned to begin in February 2025.
- Summer 2022 – Project launch
- Fall 2022 – Existing conditions analysis
- September-October 2022 – Engagement Opportunity 1: Gather input on safety needs in the corridor and ideas for corridor alternatives
- November-December 2022 – Corridor Alternatives Development
- January 2023 – Engagement Opportunity 2: Review the corridor alternatives and concepts for multimodal improvements
- Summer 2023 – Conceptual design for roadway
- Summer 2024 – Final design
- Fall 2024- Project advertised for bids
- Febrary 2025 – Construction begins
We are interested in your feedback on this project. Please fill in the form below if you have comments, questions or suggestions.