Water gushing from a damaged culvert erodes the hillside below a crumbling road.
Water gushing from a damaged culvert erodes the hillside below the slide.

Project Information

  • Location: NW Germantown Road, between Skyline and Kaiser (see location map)
  • Schedule: Right of Way acquisition (Fall 2017).  Construction: a one-week road closure will be needed in late 2017 or spring 2018 (weather dependent).
  • Estimated Cost: $120,000
  • Funding Source: Federal Emergency Funds

Project Description

A slow moving landslide has damaged a portion of NW Germantown Rd. The culvert that crosses Germantown in this section has failed, adding to the slide. We plan to repair the slope, replace the culvert, and realign the road away from the slope.

Map of Germantown Road slide repair project area

Traffic Impact

The repairs will require a closure of the road for up to one week. The road is too narrow to keep open to traffic during repairs.

Germantown will be closed to through traffic between NW Kaiser Road and NW Skyline Boulevard. Residents of Germantown will have access at all times, up to the work zone.

Alternate routes for through traffic will include NW Skyline Boulevard and Springville Road.

Public Involvement

A public meeting was held on August 30, 2017 at the Skyline Grange to share information about the project and gather community input.  The meeting presentation and public comment summary from the meeting are below.


We are interested in your feedback on this project. Please fill in the form below if you have any comments, questions or suggestions.